Q: I'm wondering about all sanctioned projects TRP has on the books ($30 billion worth I think).
Given the second round of cost overruns on the construction of the Coastal Link Pipeline, I expect actual costs to exceed the estimates used to FID these projects, probably also by significant amounts. Do you have any info on if each project will be re-assessed with a higher cost estimates to determine if they still meet their return on investment hurdle?
Given the second round of cost overruns on the construction of the Coastal Link Pipeline, I expect actual costs to exceed the estimates used to FID these projects, probably also by significant amounts. Do you have any info on if each project will be re-assessed with a higher cost estimates to determine if they still meet their return on investment hurdle?